Quick answer: The Chinese New Year 2027 factory shutdown centres on Saturday, 6 February 2027, Lunar New Year's Day, with New Year's Eve on Friday, 5 February.1 In mainland China the statutory Spring Festival holiday is four days, from New Year's Eve to the third day of the new year, which in 2027 means 5 to 8 February.2 The official 2027 holiday schedule, with its make-up working days, had not been published when we checked on 23 October 2026, but official guidance already says a Friday New Year's Eve can create a 9-day break, and it names 2027 as the example.3 Factories usually stop longer than the public holiday. In our experience at SourcingXpro, most Chinese companies are off for about two weeks, as staff add annual and personal leave, and factories with few orders may close for 20 to 30 days. With raw materials to prepare, plan about one extra month of lead time to avoid stock-outs. The deadline that matters is your supplier's own last production day and restart date, confirmed in writing.

This guide covers the confirmed 2027 dates, what is still unknown, and five order deadlines to set with your supplier for custom products: artwork, samples, packaging, cargo-ready date and shipping.

Chinese New Year 2027: what is confirmed and what is not

Some dates are fixed by the lunar calendar and by law. Others are set each year by the State Council, and some are set by each factory. Keep them apart in your plan.

Item 2027 status Source
Lunar New Year's Day Saturday, 6 February 2027 Hong Kong SAR Government gazetted 2027 holidays1
Statutory Spring Festival holiday (mainland China) 4 days: New Year's Eve to day 3, i.e. 5 to 8 February 2027 State Council Order No. 795, in force since 1 January 20252
Length of the official break Not yet announced. Officials have said a Friday New Year's Eve can give 9 consecutive days off, "for example 2027" Official Q&A on the 2024 holiday reform3
Make-up working days (weekend days worked) Not yet announced Annual State Council notice; the 2026 notice was issued on 4 November 20254
Lantern Festival (15th day of the first lunar month) Saturday, 20 February 2027 Counted from 6 February
Your factory's last production day and restart date Set by each factory Ask your supplier, in writing

For comparison, the 2026 notice set a 9-day Spring Festival break from 15 to 23 February 2026, plus two Saturday make-up working days, 14 and 28 February.4 Use that as an example of the format to expect, not as a forecast for 2027.

Chinese New Year 2027 factory shutdown: how long do factories actually stop?

Longer than the public holiday, in most cases. The official break is only the part everyone shares. Around it, each factory decides when to stop taking new work, when to stop production, and when to restart.

What we see at SourcingXpro: Most Chinese companies are off for about two weeks, not only the four statutory days, because staff add annual leave and personal leave to the legal holiday. Factories without many orders may close for 20 to 30 days. Add raw-material preparation before the stop, and our working rule is about one month of extra lead time. This is our experience in Shenzhen, not an official statistic; your suppliers' confirmed dates still decide your plan.

Three things stretch the practical gap:

  • Workers travel home before the holiday. Chinese New Year is the main family holiday of the year, and many factories employ workers whose homes are in other provinces. A factory may slow down before its official closing date.
  • Restart is gradual. An office can reopen before the production line runs at normal speed. Some workers return later, and some may not return, so the first weeks back can be slower.
  • Suppliers depend on other suppliers. A finished promotional product often needs raw materials, printing, packaging and accessories from different workshops. Each one has its own calendar.

There is no single closure date for "Chinese factories". If someone gives you one, ask where it comes from. The only dates you can plan on are the ones your own suppliers confirm.

For a broader look at how holidays fit into production time, see our guide to how long it takes to produce custom promotional products in China.

Why custom and promotional orders feel the holiday first

A stock product with a simple logo has few steps before production. A custom or promotional order has more approvals, and each approval is a chance to miss the pre-holiday window.

Step Why it matters before Chinese New Year What to confirm
Artwork and digital proof Production cannot be booked until the logo file, colours and position are approved Who signs off, and by which date
Physical or pre-production sample Sample time and courier time are separate clocks; a late sample can push bulk production past the factory's last working day Sample type, ready date and review address
Materials and colour Special materials or colour-matched parts may need to be ordered before the supplier's own suppliers close Material lock date
Packaging printing Gift boxes, sleeves and inserts are often made by a separate printer with a separate schedule The packaging printer's own closure date
Multi-supplier kits A kit is only ready when its last component arrives, is counted and packed One receiving and packing date for the whole set
Inspection and rework If a check finds a problem, there may be no time to fix it before the holiday Inspection date, and what happens if rework is needed

This is the gap in most Chinese New Year guides, which are written from a freight point of view. For a promotional order, the bottleneck is often an approval on the buyer's side, not the ship.

Stacks of wrapped cartons in a warehouse, representing goods packed and cargo-ready before the Chinese New Year 2027 factory shutdown

Five order deadlines to set with your supplier

These are milestones, not fixed calendar dates. Ask each supplier to put a date against each one for your order.

  1. Specification and quote locked. Product, quantity, logo method, packing and destination are final, and the quote reflects them. If anything changes later, ask for a documented re-quote and a revised schedule.
  2. Artwork and sample approved. Give one person authority to approve. Approve the sample in writing, including colour, logo position and packaging.
  3. Materials and packaging booked. Ask the supplier to confirm that materials are ordered and that the packaging printer has your job in its pre-holiday schedule.
  4. Cargo-ready date before the factory's last working day. Production finished, inspected and packed, with final carton count, size and weight. Leave a buffer for rework.
  5. Shipping booked against the forwarder's cut-off. Ask your forwarder for its last cargo-receiving date before the holiday for your route, and book once the cargo-ready date is credible.

If one of these cannot be met, decide early whether to simplify the product, split the order, change the shipping method or plan for delivery after the holiday. A clear "after the holiday" plan is better than a hopeful "before the holiday" one. If you sell from stock, reorder about one month earlier than usual so you do not run out after the holiday.

A back-planning check for orders due before the holiday

Our promotional products lead-time guide uses working planning ranges counted back from the in-hands date: 8 to 12 weeks for a stock product with a logo, 10 to 16 weeks for stock structure with custom colour or packaging, and 12 to 20+ weeks for a fully custom product or multi-item kit. They are planning ranges, not delivery promises.

Counting those ranges back from Friday, 5 February 2027 (New Year's Eve) gives these start dates:

Order type Working range Start the project between Status on 23 October 2026
Stock product + logo 8 to 12 weeks 13 November and 11 December 2026 Still possible if you start now
Stock structure + custom colour or packaging 10 to 16 weeks 16 October and 27 November 2026 Inside the window; start now
Fully custom product or multi-item kit 12 to 20+ weeks 18 September and 13 November 2026 Already tight; check feasibility first

Two cautions apply. First, this counts back to the start of the holiday, but your factory may stop earlier, so its last working day moves every date forward. Second, an in-hands date before the holiday means the goods have also cleared transit and customs in your country. If your goods are needed in February or March, treat the holiday weeks as non-working time and add them to the schedule. In our experience, that adds about one month to any order that crosses the holiday, including raw-material preparation.

Shipping around Chinese New Year

Freight is part of the same calendar. Before the holiday, many exporters try to ship at the same time, and forwarders and carriers set their own last receiving dates.

Container port with cranes and stacked shipping containers, illustrating pre-holiday shipping cut-offs from China

Situation Practical choice
Cargo ready well before the factory closes Book sea or air freight early and confirm the forwarder's receiving cut-off
Cargo ready close to the closing date Compare air or express against waiting; confirm warehouse receiving dates
Cargo will not be ready in time Plan to ship after the holiday and tell your own team the new in-hands date now
Multi-supplier order Confirm when the consolidation warehouse stops receiving and when it reopens

A shipment that leaves before the holiday can still arrive after your deadline. Ask for the arrival estimate and the delivery to your door, not only the departure date.

After the holiday: restart and quality risk

The first weeks after Chinese New Year deserve their own plan.

  • Confirm the real restart date. Ask when production, not the office, will restart for your order.
  • Re-confirm your specification. If the line restarts with some new staff, make sure the approved sample and specification are in front of the team.
  • Keep inspection in the plan. An order that starts after a break should be checked against the approved sample before shipment.
  • Re-check material prices and availability. If materials were not bought before the holiday, ask whether the quote still holds.

Pre-holiday checklist for buyers

  • Write down the required in-hands date for each order.
  • Ask each supplier for its last production day, office closing date and restart date, in writing.
  • Ask packaging printers and component suppliers the same question, or ask your main supplier to confirm them.
  • Lock specifications and approve artwork and samples as early as possible.
  • Agree the cargo-ready date and inspection date.
  • Ask your forwarder for pre-holiday cut-offs on your route.
  • Decide in advance what you will do if the pre-holiday date is missed.
  • Note the official 2027 schedule once the State Council publishes it, and update your plan.

If your quote request is still incomplete, use our checklist of what information you need for a promotional product quote before you send it.

FAQ

1. When is Chinese New Year 2027?

Lunar New Year's Day is Saturday, 6 February 2027, and New Year's Eve is Friday, 5 February 2027.1 The Lantern Festival, the 15th day of the first lunar month, is Saturday, 20 February 2027.

2. How long is the official Chinese New Year holiday in 2027?

The statutory holiday is four days, 5 to 8 February 2027.2 The full break with make-up working days is set by the State Council's annual notice, which was not yet published when we checked on 23 October 2026. Official guidance has said a Friday New Year's Eve can give a 9-day break and used 2027 as the example.3

3. When do Chinese factories close for Chinese New Year 2027?

Each factory sets its own dates, and many stop before the official holiday and restart after it. In our experience, most companies are off for about two weeks, and factories with few orders may close for 20 to 30 days. Ask your supplier for its last production day and restart date in writing.

4. When should I place orders before Chinese New Year 2027?

Work back from your in-hands date and your supplier's last working day. Using our lead-time guide's planning ranges, a fully custom product or kit due before the holiday should have started between mid-September and mid-November 2026. Simpler stock-plus-logo orders have more room, but should start now. For restocking, add about one month of lead time to avoid a stock-out after the holiday.

5. Can I ship goods from China during Chinese New Year?

Some logistics services may keep operating, but the factories, warehouses and suppliers that your shipment depends on may be closed. Confirm receiving and cut-off dates with your forwarder before you plan on it.

6. Is it safe to place an order right after Chinese New Year?

Yes, if you plan for a slower restart. Re-confirm the specification, the restart date and the inspection before shipment.

Plan your 2027 order before the factories close

Send SourcingXpro your product, quantity, logo, packaging needs, destination and required in-hands date. We will help you map the pre-holiday milestones, confirm the supplier dates that matter, and tell you honestly whether "before Chinese New Year" is still realistic or whether an after-holiday plan is safer. For restocking, we will help you build in about one extra month of lead time so you do not run out of stock. Start your promotional gift inquiry here.

Sources


  1. GovHK, "General holidays for 2027", https://www.gov.hk/en/about/abouthk/holiday/2027.htm. Lists Lunar New Year's Day as Saturday, 6 February 2027 (used here for the lunar calendar date only; Hong Kong holidays differ from mainland China). Checked 23 October 2026. ↩

  2. State Council of the PRC, "Decision on Amending the National Holidays and Commemorative Days Regulation (Order No. 795)", https://www.gov.cn/zhengce/content/202411/content_6986380.htm, 12 November 2024. Sets a 4-day Spring Festival holiday from 1 January 2025. ↩

  3. Chongqing Municipal Government, "official Q&A on the 2024 holiday reform", https://www.cq.gov.cn/zwgk/zfxxgkml/hygq/202411/t20241113_13794120_wap.html, 13 November 2024. Explains that a Friday New Year's Eve can give a 9-day break, "for example 2027". ↩

  4. General Office of the State Council, "Notice on 2026 Holiday Arrangements", https://www.gov.cn/zhengce/content/202511/content_7047090.htm, 4 November 2025. Set the 2026 Spring Festival break (15 to 23 February) and make-up working days. ↩